Gantt Chart

The team created a Gantt Chart to ensure the Water Harvesting System senior design project is completed in a smooth and timely manner. The timeline shows which steps are necessary as a prerequisite, how long each task is estimated to take, and which team members are responsible for each task. Click               to view the Gantt Chart uploaded as a PDF document, or see the important aspects of the Gantt Chart below. 

​

The project is divided into six phases that each have different focuses. Phases 1-3 are aimed at concept selection, development, and technical analysis, while Phases 4-6 are focuses on physical construction of the prototype, testing the system, and optimizing the results. The start date of the project was September 19, 2019 and the end date is May 1, 2020.

​

The piece-wise timeline above shows the full perspective of tasks and dates required in order for the team to meet the final deadline of May 1st (the Innovation Expo).

​